AutoCreating a Standard Purchase Order
Purpose
Use this procedure to create a purchase order from a requisition.
Trigger
Perform this procedure when a requisition appears in the queue
Prerequisites
You have access to WVU Buyer
· A requisition has been created and forwarded to a buyer.
Menu Path
Use the following menu path(s) to begin this task:
· Select WVU Buyer and then AutoCreate.
Helpful Hints
None
· xxx
· xxx
Procedure
1. Start the task using the menu path.
Navigator – WVU Buyer
|
Find Requisition Lines
|
AutoCreate Documents
|
5. Review the category, description, amount, etc., for accuracy.
6. Click the checkbox to the left of the requisition number. The selected row becomes blue.
7. Keep the default Document Type Standard PO.
Document Type
|
New Document
|
|
Purchase Order Summary to Purchase Orders
|
11. Copy the purchase order number in the PO, Rev field with a Control C command.
12. To requery and verify that the DFF information has traveled to the purchase order from the requisition, select ViewèQuery By ExampleèEnter. The purchase order is cleared from the screen.
13. Paste the purchase order number into the PO, Rev field with a Control V command.
14. Select ViewèQuery By ExampleèRun. The screen is refreshed.
Purchase Order Summary to Purchase Orders
15. Verify that the DFF information is visible.
The header DFF is to the right of the Total
field. The Lines DFF is the last column
on the right of each Purchase Order Line.
Descriptive Flexfields
|
Purchase Order Summary to Purchase Orders
|
16. To see if an attachment has been associated with the document, look at the paper clip icon in the toolbar while clicking in the header and in all purchase order lines. If an attachment has been created, a piece of paper will be attached to the paper clip icon.
Attachment Icon
|
If the piece of paper appears while the
cursor is in the header, then the attachment is associated with the entire
purchase order. If the piece of paper
appears while the cursor is in a line, then the attachment is associated with
the line only.
Oracle Applications
|
Attachment Screen
|
17. Review the attachment and then return to
the main screen by clicking the in the upper right corner.
Purchase Order Summary to Purchase Orders
|
18. Click to copy the Ship-To location into the purchase
order header.
Shipments
|
19. Highlight the address in the Ship-To field
with a Control C command and exit this screen by clicking the in the upper right corner.
Purchase Order Summary to Purchase Orders
|
20. Click in the Ship-To field and paste the address using a Control V command.
Purchase Order Summary to Purchase Orders
|
21. Click the DFF in the header. This is to the right of the Total .
Header DFF
|
22. Complete the following fields:
Field Name |
R/O/C |
Description |
BUYER CODE/INITIALS |
R |
The buyer’s initials. Example: HD |
Select Logo to Print |
R |
The logo that will appear on the Purchase Order. Example: WV
|
24. Perform one of the following:
If |
Go To |
If the purchase Type is Equipment |
Step 25 |
If the purchase Type is Goods |
Step 28 |
If the purchase Type is Architect/Engineering |
Step 31 |
If the purchase Type is Construction |
Step 34 |
If the purchase Type is HazMat |
Step 37 |
If the purchase Type is Maintenance Services |
Step 40 |
If the purchase Type is Rental |
Step 43 |
If the purchase Type is 48 Service Agreement, Lease Purchase, Repairs, or Services |
Step 46 |
25. Tab to the end of the purchase order line to verify the DFF has been completed.
PO Lines: Type Equipment
|
27. Go to step 48.
28. Tab to the end of the purchase order line to verify the DFF has been completed.
PO Lines: Type Goods
|
30. Go to step 48.
31. Tab to the end of the purchase order line to verify the DFF has been completed.
PO LInes: Type Architect/Engineering
|
33. Go to step 48.
34. Tab to the end of the purchase order line to verify the DFF has been completed.
Requisition Lines: Type Construction
|
36. Go to step 48.
37. Tab to the end of the purchase order line to verify the DFF has been completed.
Requisition Lines Type Hazmat
|
39. Go to step 48.
40. Tab to the end of the purchase order line to verify the DFF has been completed.
Requisition Lines Type Maintenance Services
|
42. Go to step 48.
43. Tab to the end of the purchase order line to verify the DFF has been completed.
Requisition Lines Type Rental
|
45. Go to step 48.
46. Tab to the end of the purchase order line to verify the DFF has been completed.
Requisition Lines Fiscal Year
|
Shipments
|
49. Verify that the ship-to site and quantity have defaulted into the Shipments screen.
Distributions screen
|
51. Verify that the correct amounts have populated the Quantity fields.
52. Tab to the Charge Account field.
53. Click the Edit icon to view the account
numbers and their descriptions .
54. Verify that the Line Item is correct.
Charge Account
|
55. Perform one of the following:
If |
Go To |
The Project segment contains a number beginning with a ‘1’ |
Step 56 |
The Project segment contains 99999999 |
Step 58 |
Distributions
|
57. Verify that the POETA segments, Date field, and quantity have all been completed.
58. Perform one of the following:
If |
Go To |
If the items were purchased on a higher education or statewide contract |
Step 59 |
If the items were not purchased with a higher education or statewide contract |
Step 62 |
59. Tab to the DFF to enter Payment Authorization information if the items/services were purchased with a contract.
PO Distributions
|
60. Complete the following fields:
Field Name |
R/O/C |
Description |
SWC, GSA, Other, NO |
R |
The contract number should be written in upper case letters and should not contain hyphens or dashes. Example: U01WORK5 |
Payment Authorization |
R |
The code needed for invoice information. Example: CB |
62. Click in the upper right corner to exit the
Distributions screen.
63. Click .in the upper right
corner to exit the Shipments screen.
64. Click the Save icon in the toolbar.
Approve Document
|
This creates an Obligation Encumbrance in
the General Ledger.
67. Perform one of the following:
If |
Go To |
You are allowed to approve the purchase order because the dollar amount is under your approval limit |
Step 68 |
You are required to submit the purchase order for further approval(s) because the dollar amount of this purchase order is above your approval limit. |
Step 73 |
Note
|
Note
|
Note
|
72. You have completed this task.
Approve Document
|
The default approver’s name populates the
Forward To field.
Note
|
Note
|
76. You have completed this task.
You have created a purchase order. You have either approved it, or sent it the next approval level.
Comments